This Costing and Pricing Tool page is used to view the total calculated project price and breakdown based on external fund scheme contributions.
The fields and calculations differ for consultancy projects and non-consultancy projects. Refer to the relevant section in this help page.
For consultancy projects with the Use Price Adjustment? = Yes setting in an applicable Project Type Level funding rule, see: Project Price (adjustments).
This page supports the Costing and Pricing Tool (CPT), which was implemented in version 7.7.0 in mid-2021. Research Costing and Pricing (ReCaP) is a separate tool.
Menu path: Access CPT via a toolbar button in a Project record or button/link in an RPR eForm application
To view this page and change editable elements:
You need to have access to the Project Price page CPT018 via either a role or User Page Views.
The Project Price page is broken up into the following different sections for non-consultancy projects (if Apply Consultancy Rates? = No):
This section provides details about the settings for percentages and GST that may be involved in the price calculation. Not all may display or apply.
Default Field Label (in alphabetical order) |
Description |
Contingency Percentage |
Default: From the applied rule but can be changed Percentage applied to the cost and price to account for the risk that the project may not be undertaken as planned |
GST Percentage |
Read only; if Include GST? is No, displays as 0 Percentage applied to the total price of the project, as defined in the GST% field in System Preferences |
Include GST? |
Default: From the applied rule but can be changed Indicates whether to include additional totals with GST calculated in the price GST is not applied to internal fund schemes. |
Margin Percentage |
Only editable if User can override Margin Percentage? is Yes in the applied rule Percentage applied to calculate the difference between the cost and price for the project |
This section provides details related to the external fund schemes for the project that may be involved in the price calculation.
Default Field Label (in alphabetical order) |
Description |
(Fund Scheme Name) |
Name of the external fund scheme for the project Note: To avoid overlapping, fund scheme names that are longer than the set column width in the page design are truncated with ellipses at the end. The column width is set in the page design to allow for other fields in this section for different layouts based on the type of project. This cannot be changed. |
Capped Amount |
Only editable if Capped Price? is Yes Maximum amount the funder is willing to provide (without GST) Validation messages linked to the field are: • If
the Total Price is less
than the Capped Amount,
the following message displays "(fund scheme name) - Total
Price is less than the Capped Amount, please revisit the costing,
enter a markup amount or CLICK
HERE (link) to
automatically add the markup." If you click the link, the
markup amount is calculated (Total Price - Capped Amount) and
added to the Markup/Discount
(+/-) field. • If
the Total Price is more
than the Capped Amount,
the following message displays: See also: Markup or Discount (+/-) |
Capped Price? |
Default: No Indicates if the funder has specified a maximum price they are willing to pay When marked as Yes, you can enter a value in the Capped Amount field (above). This value will not include GST. |
ICR Waiver |
Only if Allow Indirect Cost Recovery Waiver? is Yes in Institution Level rules Not displayed if Allow Indirect Cost Recovery for Internal Fund Schemes? is No in Institution Level rules and the fund scheme is internal Select whether to enter an amount or percentage A second field displays to enter the value based on the selection: • If an amount, it cannot be greater than the total ICR amount. • If a percentage, it cannot be greater than 100. The waiver amount is listed in the Price Calculation section as Less: ICR Waiver and is shown as a negative value. |
Markup or Discount (+/-) |
Amount as either a markup to increase the price (positive value), or discount (negative value) to reduce the price If there is a funder Capped Amount defined, this field can be populated with the difference for that funder via a link in a message |
This section provides a breakdown of the values used in calculating the price of the non-consultancy research project.
The price reflects what external funders will pay for the project.
Internal fund schemes are not included in this page or in price calculations. See instead: Institution Cash and In-kind Contributions.
Important note: Different lines display depending on the ICR settings, and whether the Competitive Neutrality Charge or the ICR waiver are used.
Default Field Label |
Description |
Add: Competitive Neutrality Charge |
Only if Include Competitive Neutrality Charge? is Yes in Institution Level rules Amount added to the price of the project for a funder for CNC, as entered in a Fund Scheme RIC grid in an eForm for the fund scheme |
Contingency |
Calculated value to account for the risk that the project may not be undertaken as planned, using the percentage shown in the Price Calculation Parameters section on this page (Direct Cost Recovery + ICR) x Contingency % from the applicable rule |
Direct Cost Recovery |
Calculated value to recoup direct costs Sum of the following for cash amounts allocated to the fund scheme: • Salary Price: Internals (cash) • Salary Price: New Staff (cash) • Consumable and Capital Items (cash) • Salary Price: Externals (cash) • HDR Student Scholarship (cash) • Facility Cost (cash) |
GST |
Calculated GST value, if GST is applied to the price, using the defined GST percentage defined in the GST% field in System Preferences Total Price x GST% |
ICR - Direct Salary |
Only if ICR Method is Institution Direct Salary Cost or Mixed Calculated value to recoup indirect salary costs [Salary Price: Internals (cash) + Salary Price: New Staff (cash)] x Institution Direct Salary Cost ICR % from the applied rule for pricing |
ICR - Other Direct Cost |
Only if ICR Method is Mixed Calculated value to recoup other direct costs [Consumable and Capital Items (cash) + Salary Price: Externals (cash) + Facility Cost (cash) + HDR Student Scholarship (cash)] x Other Direct Cost ICR % from the applied rule for pricing |
ICR - Total Direct Cost |
Only if ICR Method is Total Direct Cost Combined value to recoup direct costs Direct Cost Recovery x Total Direct Cost ICR % from the applied rule for pricing |
Less: ICR Waiver |
Only shown if Allow Indirect Cost Recovery Waiver? is Yes in Institution Level rules Reduction of Indirect Cost Recovery (ICR) from the price of the project based on the value entered in the ICR Waiver fields in this page (negative amount or percentage) • If a percentage is entered, ICR Waiver = Total ICR x entered percentage • If an amount is entered, ICR Waiver = entered amount |
Margin |
Calculated difference between the cost and the price of the project, calculated with the Margin Percentage shown in the Price Calculation Parameters section on this page (Direct Cost Recovery + ICR + Contingency ) x Margin % from the applicable rule |
Markup or Discount (+/-) |
Adjustment to the price, to either increase the price (positive value) as a markup, or reduce the price (negative value) as a discount |
Total Cash Contribution |
Calculated cash amounts provided by the funder without GST Direct Cost Recovery + ICR + Contingency amount + Margin amount + Markup or Discount + CNC - ICR Waiver |
Total incl. GST |
Total cash amount provided by the funder plus the GST amount Total Cash Contribution + GST |
Default Field Label |
Description |
Total In-kind Contribution |
The total of all in-kind values for the external funder Depending on project inputs, this may include: • Consumable and capital item costs for items provided to your institution • Facility costs for facilities provided to your institution Indirect Cost Recovery is not applied to in-kind contributions. |
Administrators: By default, only the Total In-kind Contribution amount is displayed. If you want to display a more detailed breakdown, change the layout of the Page View for this page.
For the total project amount, go to the Totals section on the left panel of the tool.
The Project Price page is broken up into the following sections for consultancy projects (if Apply Consultancy Rates? = Yes) unless a Project Type Level funding rule applies and has both of the following settings: a) Use Pricing for Consultancy Projects? = Yes and b) Use Price Adjustment? = Yes. If so, the Project Price with adjustments page displays instead. See: Project Price (adjustments)
• Consultancy projects will have only one external fund scheme and no internal fund scheme.
• There is no In-kind contribution by the funder in consulting projects.
• Contingency and margin do not apply to consultancy projects.
This section provides details about the settings for GST that may be involved in the price calculation for consultancy projects.
Default Field Label (in alphabetical order) |
Description |
GST Percentage |
Read only; if Include GST? is No, displays as 0 Percentage applied to the total price of the project, as defined in the GST% field in System Preferences |
Include GST? |
Default: From the applied rule but can be changed Indicates whether to include additional totals with GST calculated in the price |
This section provides details related to the fund schemes for the consultancy project that may be involved in the price calculation.
Default Field Label (in alphabetical order) |
Description |
(Fund Scheme Name) |
Name of the fund scheme for the project |
(Organisation) |
Read only; displays if the CPT Configuration setting Fund Scheme Rules based on Funding Organisation? is Yes Name of the organisation for the fund scheme |
Capped Amount |
Only editable if Capped Price? is Yes Maximum amount the funder is willing to provide (without GST) Validation messages linked to the field are: • If
the Total Price is less
than the Capped Amount,
the following message displays "(fund scheme name) - Total
Price is less than the Capped Amount, please revisit the costing,
enter a markup amount or CLICK
HERE (link) to
automatically add the markup." If you click the link, the
markup amount is calculated (Total Price - Capped Amount) and
added to the Markup/Discount
(+/-) field. • If the Total Price is more than the Capped Amount, the following message displays: "(fund scheme name) - Total Price is more than the Capped Amount, please revisit the costing, enter a discount amount or CLICK HERE (link) to automatically add the discount." If you click the link, the discount amount is calculated (Total Price - Capped Amount) and added to the Markup/Discount (+/-) field as a negative value. See also: Markup or Discount (+/-) |
Capped Price? |
Default: No Indicates if the funder has specified a maximum price they are willing to pay When marked as Yes, you can enter a value in the Capped Amount field (above). This value will not include GST. |
ICR Waiver |
Only if Allow Indirect Cost Recovery Waiver? is Yes in Institution Level rules Select whether to enter an amount or percentage A second field displays to enter the value based on the selection: • If an amount, it cannot be greater than the total ICR amount. • If a percentage, it cannot be greater than 100. The waiver amount is listed in the Price Calculation section as Less: ICR Waiver. |
Markup or Discount (+/-) |
Amount as either a markup to increase the price (positive value), or discount (negative value) to reduce the price If there is a funder Capped Amount defined, this field can be populated with the difference for that funder. |
This section provides a breakdown of the values used in calculating the price of the consultancy project.
The price reflects what an external funder will pay for the project.
Important note: Different fields display depending on the ICR settings.
Default Field Label |
Description |
GST |
Calculated GST amount, if GST is enabled and applied to the price Total Price x GST% as defined in the GST% field in System Preferences |
ICR - Direct Salary |
Only if ICR Method is Institution Direct Salary Cost or Mixed Calculated indirect cost recovery value to recoup direct salary costs Salary Cost x Institution Direct Salary Cost ICR % from the applied rule for pricing |
ICR - Other Direct Cost |
Only if ICR Method is Mixed Calculated value to recoup other direct costs (Consumable and Capital Items + Facility Cost) x Other Direct Cost ICR % from the applied rule for pricing |
ICR - Total Direct Cost |
Only if ICR Method is Total Direct Cost Combined value to recoup total direct costs (Salary Cost + Consumable and Capital Items Cost + Facility Cost) x Total Direct Cost ICR % from the applied rule for pricing |
Markup or Discount (+/-) |
Adjustment to the price, to either increase the price (positive value) as a markup, or reduce the price (negative value) as a discount |
Other Direct Cost |
Calculated cost of non-salary expenses allocated to the fund scheme, such as consumable and capital items and facility costs Consumable and Capital Items costs + Facility costs allocated to the fund scheme |
Researcher RIA |
Margin +/- Markup or Discount |
Salary Cost |
Calculated cost of team member salaries (new staff and investigators with a type that is not External) allocated to the fund scheme Total salary costs allocated to the primary fund scheme |
Total Price |
Calculated total price without GST Salary Cost + Other Direct Cost + ICR amount + Margin amount + Markup or Discount |
Total Price incl. GST |
Calculated price including the GST value Total Price + GST amount |
This section provides a total of the in-kind contribution provided by external funders for the research project. Indirect Cost Recovery is not applied to in-kind contributions.
Depending on project inputs, these may include:
• Consumable and capital item costs for items provided to your institution
• Direct Cost Recovery
• Facility costs for facilities provided to your institution
By default, only the Total In-kind Contribution amount is displayed. If you want to display a more detailed breakdown, change the layout of the Page View for this page.
Note: Indirect Cost Recovery is not applied to in-kind contributions.
For the total project amount, go to the Totals section on the left panel of the tool.
Options |
Description |
Save |
Saves your changes made in this page |
Outputs |
Costing and pricing outputs available for the project and your role Outputs with CPT data are created and managed by your RME administrators or office staff. They can be provided for different purposes, funders or stakeholders. For output filter configuration, see: Output Configuration |
Close |
Returns you to the eForm costing and pricing summary page that has the button/link to open the tool |
The panel on the left includes a list of the pages available. Page status indicators are used to inform you about the status of each page.
The Totals section at the bottom of the panel displays an overview of the project totals (read only). See: Project Summary, Totals
Costing and Pricing Tool pages:
• Consumable and Capital Items
• Institution Cash and In-kind Contribution
Reference:
Costing and Pricing Tool configuration:
• Salary and Indexation configuration
Product key: Costing and Pricing Tool